| INSTALLATION PROCEDURE | ||||
1. |
Locate positions of joist ends and mark on the external side of wall. | |||
2. |
Drill
12mm clearance holes through masonry in line of and centre of the joist
ends. |
|||
3. |
Clear hole of any dust or loose debris using an air pump. | |||
4. |
Load PAM Bow-Fix into support tool and insert through clearance hole, then hammer PAM Bow-Fix into joist end to the required depth. | |||
5. |
Inject PAM Resin into hole and completely fill. | |||
6. |
Make good surface of holes using colour matching dyed mortar. | |||
| INSTALLATION NOTES | ||||
| UNLESS SPECIFIED OTHERWISE THE FOLLOWING CRITERIA ARE TO BE USED: | ||||
a. |
Minimum penetration depth into end grain of timber to be 50mm. | |||
b. |
Install PAM Bow-Fix into every joist end in area concerned. | |||