<%@LANGUAGE="VBSCRIPT" CODEPAGE="CP_ACP"%> Fixing PAM Bow-Ties into Joist Ends - Timber Frames
You are here - Homepage > Lateral Restraints > Fixing PAM Bow-Ties into Joist Ends - Timber Frames

 
o o o o o
 
 
INSTALLATION PROCEDURE  
     
1.
Locate positions of joist ends and mark on the external side of wall.  
2.
Drill 12mm clearance holes through masonry in line of and centre of the joist ends.
 
3.
Clear hole of any dust or loose debris using an air pump.  
4.
Load PAM Bow-Fix into support tool and insert through clearance hole, then hammer PAM Bow-Fix into joist end to the required depth.  
5.
Inject PAM Resin into hole and completely fill.  
6.
Make good surface of holes using colour matching dyed mortar.  
     
 
 
INSTALLATION NOTES  
     
  UNLESS SPECIFIED OTHERWISE THE FOLLOWING CRITERIA ARE TO BE USED:  
     
a.
Minimum penetration depth into end grain of timber to be 50mm.  
b.
Install PAM Bow-Fix into every joist end in area concerned.